AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA


Department Of Quantity Surveying


PAGES: 56
FORMAT: MS WORD
Chapters: 1-5
PRICE: ₦ 5,000.00

AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA

ABSTRACT

The importance of accurate estimates during the early stages of cost planning of capital projects has been widely recognized for many years. Even so, very few quantitative methods are available that enable estimators and business managers to objectively evaluate the accuracy of early estimates and planning.

The primary purpose of this study was to identify and examine the factors affecting accuracy of cost planning of building projects as it relate to the Nigerian construction industry. To accomplish this aim, quantitative data were collected from consultant Quantity Surveyors. Each of the respondents was asked to assign a one-to-ten rating for each of 10 potential drivers of estimate accuracy for a given estimate. The data were analyzed using simple statistical tools which include; mean, standard deviations and percentages were used to represent the information.  The study analysis identified 5 of the 10 factors that were most significant at the  level. In this finding the five factors, in order of significance were, Amount of information available, Time allowed to prepare the estimate, Experience of the consultant team, Complexity of the project, and bidding and Suitability/stability of the market.

Cost estimating and planning is a fundamental part of the construction industry. The success or failure of a project is dependent on the accuracy of several estimates through-out the course of the project. Construction estimating is the compilation and analysis of many items that influence and contribute to the cost of a project. Estimating which is done before the physical performance of the work requires a detailed study and careful analysis of the bidding documents, in order to achieve the most accurate estimate possible of the probable cost consistent with the bidding time available and the accuracy and completeness of the information submitted. Overestimated or underestimated cost has the potential to cause loss to local contracting companies.

                  TABLE OF CONTENTS

Title page………………………………………….……………………………………………i

Declaration…………………………………………….………………………………………ii

Certification………………………………………………….……………………………….iii

Dedication…………………………………………………………………………………….iv

Acknowledgement………………………………………………………………………….….v

Abstract………………………………………………………………………………………vii

Table of content…………………………………………………..…………………………viii

Table of figures……………………………………………………………………………….ix

List of tables……………………………………………………………………….…………..x

CHAPTER ONE

1.1  INTRODUCTION………………………………………………...………………….….1

1.2  Statement of the problem…………………………………………..…………………..…3

1.3.0  Aim and objectives…………………………………………..………………………….4

1.3.1  Aim………………………………………………………….…………………………..4

1.3.2  Objectives………………………………………………………….....…………………4

1.4.0  Scope and limitation……………………………………………...……………………..4

1.4.1  Scope…………………………………………………………………………...…….…4

1.4.2  Limitation…………………………………………..……………………………..…….5

CHAPTER TWO

2.0               LITERATURE REVIEW………………………………………..…………….…...…6

2.1.1        Cost planning………………………………………………………………...……...…6

2.1.2      History and Development of cost planning…………………………….…..……...…6

2.2.0        Cost control………………………………………………………………….……..….7

2.21           Definition………………………………………………………………………….….7

2.2.2        Cost plan………………………………………………………….……………………8

2.3              Approximate estimating………………………………….……………...…………….8

2.4.0     Concept of cost planning………………………………………………………..…….9

2.4.1        Preliminary cost planning ………………………………………..…………………..10

2.4.2        Cost planning reports…………………………………………..………………….…10

2.5.0        Cost Planning techniques/methods………………………………………………..….12

2.5.1        Various cost planning techniques……………………………………………...……..12

1.5.1.1  Easy cost planning (ECP)……………………………………………………………12

2.5.1.2  Network costing………………………………………………………………….….13

2.5.1.3  Detailed costing………………………………………….…………………………..13

2.5.1.4 Unit costing……………………………………………………………….………….14

2.5.2        Elemental cost planning…………………………………………………………...…14

2.5.3        Comparative cost planning……………………………………………………..…….15

2.6              Uses of cost planning………………………………………….…………..…………15

2.7              Factors affecting the accuracy of cost planning………………...……………………16

2.7.1        Location factor……………………………………………………………….………16

2.7.2        Design factor…………………………………………………………….…………...17

2.7.3        Qualitative factor…………………………………………………………..…………19

2.7.4        Construction factor…………………………………………….……………………..19

2.7.5        Time factor……………………………………………..……………………….……19

2.7.5.1  Project complexity……………………………………………………………………20

2.7.5.2  Availability/amount of project information…………………………….……………20

2.7.5.3  Technological factor………………………………………………………….………21

2.7.5.4  Contract requirements/stage of work………………………………...………………21

2.7.5.5  Team’s/contractor’s/consultant’s experience and efficiency……….………………..21

2.7.5.6  Stability of market/market requirement………………………………...……………21

CHAPTER THREE

3.0     RESEARCH METHOD………..……………………………………………...………25

3.1     Population and sample………………………………………………………………....25

3.2     Survey method……………………………………………………………………….…26

CHAPTER FOUR

4.0     DATA PRESENTATION, ANALYSIS AND INTERPRETATION………………..28

4.1     Data collection…………………………………………………………...……..………28

4.2     Data presentation and analysis……………………………....………………..………..30

CHAPTER FIVE

5.0    CONCLUSION AND RECOMMENDATION………….……………………....…….50

5.1    Conclusion………………………………………………………………………..……..50

5.2    Recommendation………………………………………….…………………….………52

References and Bibliography………………………………………………………………...54

APPENDICES

APPENDIX I………………………………………………………….………………..……59

LIST OF TABLES

Table 4.1.0: Description of data collection from questionnaire survey28

Table 4.2.0: Summary of results’ table showing how often the respondents prepare cost plans for building, civil engineering, heavy engineering, and services works

Table 4.2.1: Percentage ranking of work type showing how often the respondents prepare cost plans for building, civil engineering, heavy engineering, and services works…………………………………………….33

Table 4.2.2: Respondents' preparation of cost plans for their organization……………………………………35

Table 4.2.3: percentage of building projects handled in which cost plans were prepared by  respondents………………………………...36

Table 4.2.4: Method(s) used for preparation of cost planning………………………………………………………….37

Table 4.2.5: Cost planning method(s) that is/are mostly used in the respondents' organization………38

Table 4.2.6: Respondents’ reason for choosing a given cost planning method(s)

Table 4.2.7: Urgency of demand for cost plans when commissioned

Table4.2. 8: Adequacy of time to meet ClientsDemand for cost plans

Table 4.2.9: Source of Data mostly Used for Cost Planning

Table 4.2.10: Accuracy and Reliability of Cost Plans being Used

Table 4.2.11: Factors that affect the accuracy of cost planning of building projects

Table 4.2.12: Mean score and standard deviation for factors affecting cost planning of building projects in Nigeria              

CHAPTER ONE

INTRODUCTION

1.1              BACKGROUND OF THE STUDY

Costing in building construction is the application of price to schedules of item of labour and materials in order to obtain an approximation of cost of construction project (Ibrahim, 2004).

Cost planning of construction project is concerned with keeping the cost within a predetermined cost estimate during the pre-contract and post-contract stages of the construction works. The process of pre-contract cost planning involves the preparation of an approximate estimate amongst others. The object of the approximate is to provide an estimate of a probable cost of a project before detail design or post-contract service (Hoer, 1997).

Today’s client needs are becoming more sophisticated and complicated leading to difficulties in estimating the probable cost of construction works. The clients themselves are becoming more sophisticated in the level of in-house technical expertise and techniques available to them and they in turn expect a high level of efficiency, accuracy and expertise from their professionals. The introduction of new construction methods, materials and systems create greater difficulties in assessing and planning for the capital and maintenance cost of construction.

Adams (1999) reported that cost planning has become more sophisticated over the last decade and is increasingly becoming a service that the employer is expecting from the Quantity Surveyor to ensure that he receives better value for money and the project cost is kept within the budget.

Cost planning of construction projects is aimed at ensuring that the resources are used to the best advantage amidst alternating high cost of construction resources and acute shortage of funds as clients increasingly insists on project designs to be executed in a way to give them better value for money when completed.

However, there are several factors that may affect the efficiency of cost planning at different stages of the project; from the pre-contract through the post-contract stage. Although, careful detailed order of work will definitely reduce these effects that lead to the large discrepancies between the tender figures and final cost of the construction.

The accuracy of cost planning is measured by how well the estimated cost can be compared to the actual construction cost (Oberleder and Trost, 2002).

            Hore (1997) stated that the level of accuracy of a cost plan depends upon the level of information availability at time of preparation.

Pre-tender cost estimating and planning of building projects requires extensive knowledge and expertise. Due to inadequate design information in the early design stages, it is extremely difficult for Quantity Surveyors to arrive at accurate cost estimates and cost planning becomes inefficient (Koleola and Henry 2008).

According to Koloela and Henry (2008), there are seven most important factors, based on the construction industry experience of the Quantity Surveyors which affect the accuracy of pre-tender cost planning.

The seven most important factors as highlighted by Koloela and Henry are; expertise of consultants, Quality of information and flow requirements, project team’s experience of the type of construction, tender period and market condition, extend of completion of pre-tender designs, complexity of design and construction, availability and supply of labour and materials.

Taking these factors into consideration at project inception stage could improve the accuracy of the preliminary cost advice consultant quantity Surveyors give their clients.

1.2               STATEMENT OF THE RESEARCH PROBLEM

It has been discovered that in practice, contractors device their own methods of cost planning and bidding and the accuracy of their methods is doubtful (Akintoye, and Fitzgerald 1999 citing Law, 1994). The importance of accurate estimates during the early stages of capital projects has been widely recognized for many years. Early project estimates represent a key ingredient in business unit decisions and often become the basis for a project's ultimate funding. However, a stark contrast arises when comparing the importance of early estimates with the amount of information typically available during the preparation of an early estimate. Such limited scope definition often leads to questionable estimate accuracy. Even so, very few quantitative methods are available that enable estimators and business managers to objectively evaluate the accuracy of early estimates. The problem here is how to establish such a model to assess the factors affecting the accuracy of cost planning. To accomplish this, quantitative data were collected from consultant Quantity Surveyors from the construction industry.

.



TYPE IN YOUR TOPIC OR KEYWORD AND CLICK SEARCH:

HOW TO GET THE COMPLETE PROJECT MATERIAL ON AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA

  • * Click the green DOWNLOAD Button above

    * Select any option to get the complete project material instantly.

    * Chat our 24/7 customer service desk on WhatsApp# (+234) 0803-766-4978 and get your complete project material instantly.

    * All project materials on this website are well researched by professionals with high level of professionalism.


TESTIMONIES FROM OUR CLIENTS

Please feel free to carefully review some written and captured responses from our satisfied clients.


  • Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.

    "Exceptionally outstanding. Highly recommend for all who wish to have effective and excellent project defence. Easily Accessable, Affordable, Effective and effective."

  • Hilary Yusuf, United States International University Africa, Nairobi, Kenya.

    "I saw this website on facebook page and I did not even bother since I was in a hurry to complete my project. But I am totally amazed that when I visited the website and saw the topic I was looking for and I decided to give a try and now I have received it within an hour after ordering the material. Am grateful guys!"

  • Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.

    "Researchwap.net is a website I recommend to all student and researchers within and outside the country. The web owners are doing great job and I appreciate them for that. Once again, thank you very much "researchwap.net" and God bless you and your business! ."

  • Lamilare Valentine, Kwame Nkrumah University, Kumasi, Ghana.

    "Great User Experience, Nice flows and Superb functionalities.The app is indeed a great tech innovation for greasing the wheels of final year, research and other pedagogical related project works. A trial would definitely convince you."

  • Sampson, University of Nigeria, Nsukka.

    "I love what you guys are doing, your material guided me well through my research. Thank you for helping me achieve academic success."

  • Cynthia, Akwa Ibom State University .

    "researchwap.com is God-sent! I got good grades in my seminar and project with the help of your service, thank you soooooo much."

  • Elizabeth, Obafemi Awolowo University

    "Sorry, it was in my spam folder all along, I should have looked it up properly first. Please keep up the good work, your team is quite commited. Am grateful...I will certainly refer my friends too."

  • Ali Olanrewaju, Lagos State University.

    "Am happy the defense went well, thanks to your articles. I may not be able to express how grateful I am for all your assistance, but on my honour, I owe you guys a good number of referrals. Thank you once again."

  • Willie Ekereobong, University of Port Harcourt.

    "My Dear Researchwap, initially I never believed one can actually do honest business transactions with Nigerians online until i stumbled into your website. You have broken a new legacy of record as far as am concerned. Keep up the good work!"

  • Theressa, Igbinedion University.

    "WOW, SO IT'S TRUE??!! I can't believe I got this quality work for just 5k...I thought it was scam ooo. I wouldn't mind if it goes for over 5k, its worth it. Thank you!"

  • Joseph, Abia state Polytechnic.

    "I did not see my project topic on your website so I decided to call your customer care number, the attention I got was epic! I got help from the beginning to the end of my project in just 3 days, they even taught me how to defend my project and I got a 'B' at the end. Thank you so much researchwap.com, infact, I owe my graduating well today to you guys...."

  • Christiana, Landmark University .
    Christiana, Landmark University .

    "My friend told me about ResearchWap website, I doubted her until I saw her receive her full project in less than 15 miniutes, I tried mine too and got it same, right now, am telling everyone in my school about researchwap.com, no one has to suffer any more writing their project. Thank you for making life easy for me and my fellow students... Keep up the good work"

  • Musa, Federal University of Technology Minna

    "I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!."

  • Ali Obafemi, Ibrahim Badamasi Babangida University, Niger State.

    "I was scared at first when I saw your website but I decided to risk my last 5k and surprisingly I got my complete project in my email box instantly. This is so nice!!!."


  • To contribute to our success story, send us a feedback or please kindly call 2348037664978.
    Then your comment and contact will be published here also with your consent.
    Thank you for choosing researchwap.com.

FREQUENTLY ASKED QUESTIONS

  • How can I get the complete project - AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA

    Simply click on the DOWNLOAD green button above and follow the procedure stated.


    Is it a complete project work or just materials?

    Yes, it's a Complete Research Project material. i.e Chapters 1-5, Abstract, Table of Contents, Full References, Questionnaires / Secondary Data


    What if I want to change the case study for AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA, What can i do?

    Chat with Our 24/7 Customer Service Desk Now: WhatsApp# and you will be responded to Instantly


    How long does it take to get the complete project on AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA?

    Depending on how fast your payment and details is acknowledged by us, you will get the complete project within 30 minutes. However, on a very good day you can still get it within 15 minutes!


    How will I get my complete project?

    The Complete Project Material will be Delivered via your Email Address in an MS Word document format


    Can I get my Complete Project through WhatsApp?

    Yes! We also send your Complete Research Project to your WhatsApp Number


    What if my Project Supervisor made some changes to a topic i picked from your website?

    Call or Chat With Our 24/7 Custumer Care Desk: +234 8037664978 and you will be responded to Instantly


    Do you assist students with Assignment, Term Paper, Seminar and Project Proposal?

    Call or Chat With Our 24/7 Custumer Care Desk: +234 8037664978 and you will be responded to Instantly


    What if i do not have any project topic idea yet?

    Don't Worry! We've Got Your Covered. Chat with us on WhatsApp# (+234) 0803-766-4978 to Get Instant Help.


    Why should I trust this website?

    We are well aware of fraudulent activities that have been happening on the internet. It is regrettable, but hopefully declining. However, we wish to reinstate to our esteemed clients that we are genuine and duly registered with the Corporate Affairs Commission as "TOPNOTCH INFOTECH ENTERPRISE". This site runs on Secure Sockets Layer (SSL), therefore all transactions on this site are HIGHLY secure and safe!


    10. I have a fresh topic that is not on your site. How do I go about it?

    Don't Worry, Chat with us on WhatsApp# (+234) 0803-766-4978 to Get Instant Help.



PROJECT DETAILS

PAGES: 56
FORMAT: MS WORD
Chapters: 1-5
PRICE: ₦ 5,000.00




TYPE TOPIC OR KEYWORD AND CLICK SEARCH: