THE IMPACT OF PROCUREMENT SYSTEMS ON CONSTRUCTION COST AND DELIVERY

 THE IMPACT OF PROCUREMENT SYSTEMS ON CONSTRUCTION COST AND DELIVERY 

CHAPTER ONEINTRODUCTION

1.1 BACKGROUND OF THE STUDY  

The construction industry is an important part of the economical backbone in manycountries (Ngai et al., 2002), often accounting for between 7-10 percent of the GrossDomestic Product (Winch, 1996, Voordijk et al., 2000). Furthermore, constructionproducts and processes have a large impact on safety, health and environmentalaspects (Bayliss et al., 2004). Since all human beings in modern societies are directlyaffected by its processes and/or products, the importance of a well-functioningconstruction industry is beyond doubt (Cheung et al., 2001, Ngai et al., 2002,Eriksson, 2007).

In many countries the construction industry has, however, attracted criticism forinefficiencies in outcomes such as time and cost overruns, low productivity, poorquality and inadequate customer satisfaction (Latham, 1994, Egan, 1998, Ericsson,2002, Chan et al., 2003). Practitioners, researchers and society at large have,therefore, called for a change in attitudes, behaviour and procedures in order toincrease the chances for construction projects to be successful and result in improvedend products (Love et al., 2000, Dubois and Gadde, 2002).

Increased complexity, uncertainty, and time pressure in construction projects haveincreased the need for cooperation among different project actors (Anvuur andKumaraswamy, 2007). Traditionally, relationships are, however, very competitive andadversarial in the construction industry (Cheung et al., 2003), which to a large extentis due to the customary procurement procedures potentially causing many problems inall stages of the buying process (Eriksson and Laan, 2007). Therefore, in order to takeadvantage of collaboration, procurement procedures is one key improvement area andcan contribute substantially to project success (Cheung et al., 2003, Eriksson, 2007). A change of procurement procedures is, however, impeded by clients’ habitualbehaviour (Laedre et al., 2006). Although procurement procedures need to be tailoredto enhance the fulfilment of different project objectives (Cox and Thompson, 1997, Love et al., 1998, Wardaniet al., 2006), clients tend to choose those procurementprocedures they have a habit of using, regardless of any differences between projects(Laedre et al., 2006). In order to enhance change, an increased understanding of howdifferent procurement procedures affect different aspects of project performance isvital. Earlier research efforts in this area have been limited to the investigation of howa single or a few specific procurement alternatives affect one or two projectobjectives. In order to achieve successful governance of construction projects aholistic and systemic approach to procurement procedures is crucial (Cox andThompson, 1997, Eriksson and Pesämaa, 2007, Eriksson, 2008b). Since a systemicperspective on the effect of procurement procedures on different aspects of projectperformance is lacking in the construction management literature, this research effortaims to fill this theoretical gap that has potential to bring important practicalimplications.

Different studies have confirmed the use ofvarious types of procurement methods for projectdelivery in Nigeria. Studies of Ogunsanmi, Iyagbaand Omirin (2003), Ojo, Adeyemi and Fagbenle (2006), and Dada (2012) all confirm the use ofTraditional, Design and Build, ProjectManagement, Construction Management, Labouronly,Direct Labour and other types such asAlliancing, Partnering and Joint Venturesprocurements in the Nigerian constructionindustry. The use of these procurement methodscan significantly affect the performance of mostprojects.

1.2 STATEMENTOF THE PROBLEM The Nigeria construction industry is modeled after the British system being our colonialmaster, although, since independence in 1960, it has incorporated the styles of other Europeancountries, such as Italy, Germany and France (Mansfield, 1994). This industry is of paramount importance foremployment and economic growth (Ogunsemi, 2004). The Nigerian construction industry forms nearly 70% ofthe nation’s fixed capital formation Federal Office of Statistics (FOS)(2004), yet its performance within the economy has been, andcontinues to be, very poor due to cost overruns resulting to abandonment of projects. For example, the Nigerian construction industry’s contribution toemployment has remained consistently at 1.0% over the last decade against the World Bank’saverage observation of about 3.2% in developing countries (Idrus, 2008). The traditional design-bid-buildsystem of procurement is still dominant in the Nigerian construction sector and this may likelycontinue to be the trend. In addition, the Nigerian construction sector comprises the clients,contractors, subcontractors, suppliers, and key professional actors responsible for design andsupervision of projects. The professionals includes architects, engineers (structural and services),and Quantity Surveyors. There are professional bodies that regulate the activities of theseprofessionals. Delay in project execution is a major problem in the Nigerian construction industry. Thisoccurs both in small and large projects. Virtually, all the projects executed over the years inNigeria were faced with problem of delay in delivery. Odeyinka and Yusuf (1997) observed thatseven out of every ten projects suffer delay in Nigeria. Nigerian construction industry is facedwith problem of cost overrun. Ogunsemi and Jagboro(2004) noted that one of the most seriousproblems the Nigerian construction industry is faced with is the project cost overrun, withattendant consequence of completing projects at sums higher than the initial sum. Therefore,working with realistic project estimate is necessary at the outset of a project work, which wouldeliminate uncertainty and as well provide a platform for project success. Idrus and Sodangi (2008) also observed that the last decade has however exposed the declining level of clients’ satisfactionfrom the built facilities as a result of poor quality performance in addition to the perennialproblems of time and cost overruns in the Nigerian construction industry. The Nigerian construction industry continues to occupy an important position in thenation’s economy even though it contributes less than the manufacturing or other serviceindustries,. This industry plays an important role in the economy, and the products of itsactivities are so vital to the achievement of national socio-economic development goals ofcreating job opportunities and social amenities and infrastructures (Anaman, 2007).

1.3 OBJECTIVES OF THE STUDY The main aim of this study is to examine procurement systems and it impact on cost management and delivery. Specific objectives of the study are:

To identify various procurement systems commonly used by quantity surveyors in Owerri. To examine challenges encountered when employing various procurement systems for construction projects. To examine the impact of procurement systems on construction cost.

1.4 RESEARCH QUESTIONS To guide the study and achieve the objectives of the study, the following research questions were formulated:

What various procurement systems commonly used by quantity surveyors in Owerri? What are the challenges encountered when employing various procurement systems for construction projects? How do procurement systemsaffect construction cost?

1.5 RESEARCH HYPOTHESES

Ho: Variations in procurement systems do not affect construction cost.

Hi: Variations in procurement systems affect construction cost.

Ho: Challenges encountered when using procurement systems contribute do not contribute to construction cost overrun.

Hi: Challenges encountered when using procurement systems contribute to construction cost overrun.

Ho: There is no significant impact between procurement systems and construction cost management and delivery.

Hi: There is a significant impact between procurement systems and construction cost management and delivery.

1.6 SIGNIFICANCE OF THE STUDY This study will be of importance to personnels in the construction industry and the general public because it would not only clarify but also create awareness of the extent to which inadequacies in cost management and procurement systems can adversely affect project performance. The study will also help contractors, clients, consultants and all parties involved in construction projects about ways of improving their current method of cost management and control. The study will also be of great benefit for other student researchers’ who may want to venture into the same subject matter. Having gotten results-both empirically and theoretically, the study will serve as a foundation for future research studies.

1.7 SCOPE OF THE STUDY The study will cover some selected contractors from Owerri. All findings and recommendations from the study may not reflect the true view of the traditional roles and changing roles of quantity surveyors as the researcher could not cover a wider area due to financial and time constraints.

1.8 DEFINITION OF TERMS

Procurement: This is the acquisition of goods, services or works from an outside external source. Procurement System: Procurement system’ is a contemporary term, which isknown to many practitioners and researchers of theconstruction industry by different terms; these includeterms such as project approach, procurement methods,procurement delivery methods or project delivery. Project Procurement: Project procurement has been described as an organized methods or process and procedurefor clients to obtain or acquire construction products. Open tendering: This is a procedure that allows practically any contractor to submit a tender for the work. This procedure involves either the client or consultant (on behalf) of the client placing a public advertisement giving a brief description of the work. Selective tendering: It consists of the client drawing up a short-list of contractors that are known to have the appropriate qualifications to carry out the work satisfactorily. Negotiated tendering: This method is applied in several or different contexts, but the essence is that tenders are obtained by the client inviting a single contractor of his/her choice to submit a tender for a particular project. Non-traditional procurement systems: This is a diversified contemporary procurement system that not only considers design and construction, but also considers financing, operating and facility management. Construction: In the fields of architecture and civil engineering, construction is a process that consists of the building or assembling of infrastructure. Far from being a single activity, large scale construction is a feat of human multitasking. Normally, the job is managed by a project manager, and supervised by a construction manager, design engineer, construction engineer or project architect. Deliverable: Deliverable is a term used in project management to describe a tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report, a document, a server upgrade or any other building block of an overall project. Project management: this is the discipline of planning, organizing, motivating, and controlling resources to achieve specific goals. A project is a temporary endeavour with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables),undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value. Time: This is a dimension in which events can be ordered from the past through the present into the future, and also the measure of durations of events and the intervals between them. Cost: A cost is the value of money that has been used up to produce something, and hence is not available for use anymore. In business, the cost may be one of acquisition, in which case the amount of money expended to acquire it is counted as cost. Cost overrun: occurs when the final cost of the project exceeds the original contract value at the time of completion. Good cost performance project: Project in which the cost overrun of the project does not exceed 10 percent of the initial budget.

REFERENCES

Anvuur, A. &Kumaraswamy, M. (2007) 'Conceptual Model

of Partnering and Alliancing'. Journal of Construction Engineering and Management, 133 (3), 225-234.

Bayliss, R., Cheung, S., Suen, H. & Wong, S.-P. (2004)

'Effective Partnering Tools in Construction: A Case Study on MTRC TKE Contract in Hong Kong'. International Journal of Project Management, 22 (3), 253-263.

Chan, D. &Kumaraswamy, M. (1997) 'A Comparative Study

of Causes of Time Overruns in Hong Kong Construction Projects'. International Journal of Project Management, 15 (1), 55-63.

Cheung, S.-O., Lam, T.-I., Leung, M.-Y. & Wan, Y.-W. (2001)

'An Analytical Hierarchy Process Based Procurement Selection Method'. Construction Management and Economics, 19 (4), 427-437.

Cheung, S., Ng, T., Wong, S.-P. &Suen, H. (2003)

'Behavioral Aspects in Construction Partnering'.International Journal of Project Management, 21 (5), 333-343.

Cox, A. & Thompson, I. (1997) 'Fit for Purpose Contractual

Relations: Determining a Theoretical Framework for Construction Projects'. European Journal of Purchasing & Supply Management, 3 (3), 127-135.

Dada, M.O. (2012), A second look: Stakeholders’

Perceptions of Some Issues in Design – Bid-Build Procurement Practice in Nigeria.Journal of Sustainable Development, 5(1), 55-63.

Eriksson, P. E. &Pesämaa, O. (2007) 'Modelling

Procurement Effects on Cooperation'.Construction Management and Economics, 25 (8), 893-901.

Latham, M. (1994) Constructing the Team. London, HMSO. Ericsson, L. E. (2002) SkärpningGubbar. SOU

2002:15,Byggkommissionen, Stockholm.

Eriksson, P. E. &Laan, A. (2007) 'Procurement Effects on

Trust and Control in Client-Contractor Relationships'. Engineering, Construction and Architectural Management, 14 (4), 387-399.

Ogunsanmi, O.E., Iyagba, R.O.A. and Omirin, M.M. (2003),

A comparative Study of the Performance of Traditional and Labour only Procurements in Nigeria.Journal of Nigeria Institute of Building, 12-27.

Laedre, O., Austeng, K., Haugen, T. &Klakegg, O. (2006)

'Procurement Routes in Public Building and Construction Projects'.Journal of Construction Engineering and Management, 132 (7), 689-696.

Love, P., Irani, Z. & Edwards, D. (2004) 'A Rework

Reduction Model for Construction Projects'.IEEE Transactions on Engineering Management, 51 (4), 426-440.

Ngai, S., Drew, D., Lo, H. P. &Skitmore, M. (2002) 'A

Theoretical Framework forDetermining the Minimum Number of Bidders in Construction BiddingCompetitions'.Construction Management and Economics, 20 (6), 473-482.

Winch, G. (1996) Contracting Systems in the European

Construction Industry: A SectoralApproach to the Dynamics of Business Systems. IN KRISTENSEN, R. W. A. P. H.(Ed.) The Changing European Firm: Limits to Convergence. London, Routledge.

Voordijk, H., de Haan, J. &Joosten, G.-J. (2000) 'Changing

Governance of Supply Chains inthe Building Industry: A Multiple Case Study'. European Journal of Purchasing &Supply Management, 6 (3-4), 217-225.

Project Topics   Project Topics and Materials   

.

Click Here To Get The Complete Project »

How To Write Chapter Three Of Your Research Project (Research Methodology)

  • Methodology In Research Paper


    Chapter three of the research project or the research methodology is another significant part of the research project writing. In developing the chapter three of the research project, you state the purpose of research, research method you wish to adopt, the instruments to be used, where you will collect your data, types of data collection, and how you collected it.

    This chapter explains the different methods to be used in the research project. Here you mention the procedures and strategies you will employ in the study such as research design, study design in research, research area (area of the study), the population of the study, etc. You also tell the reader your research design methods, why you chose a particular method, method of analysis, how you planned to analyze your data.

    Your methodology should be written in a simple language such that other researchers can follow the method and arrive at the same conclusion or findings.

    You can choose a survey design when you want to survey a particular location or behavior by administering instruments such as structured questionnaires, interviews, or experimental; if you intend manipulating some variables.

    The purpose of chapter three (research methodology) is to give an experienced investigator enough information to replicate the study. Some supervisors do not understand this and require students to write what is in effect, a textbook.

    A research design is used to structure the research and to show how all of the major parts of the research project, including the sample, measures, and methods of assignment, work together to address the central research questions in the study. The chapter three should begin with a paragraph reiterating the purpose of research. It is very important that before choosing design methods try and ask yourself the following questions: Will I generate enough information that will help me to solve the research problem by adopting this method?

    Method vs Methodology

    I think the most appropriate in methods versus methodology is to think in terms of their inter-connectedness and relationship between both. You should not beging thinking so much about research methods without thinking of developing a research methodology.

    Metodologia or methodology is the consideration of your research objectives and the most effective method and approach to meet those objectives. That is to say that methodology in research paper is the first step in planning a research project work.

    Design Methodology: Methodological Approach

    Example of methodology in research paper, you are attempting to identify the influence of personality on a road accident, you may wish to look at different personality types, you may also look at accident records from the FRSC, you may also wish to look at the personality of drivers that are accident victims, once you adopt this method, you are already doing a survey, and that becomes your metodologia or methodology.

    Your methodology should aim to provide you with the information to allow you to come to some conclusions about the personalities that are susceptible to a road accident or those personality types that are likely to have a road accident.

    The following subjects may or may not be in the order required by a particular institution of higher education, but all of the subjects constitute a defensible in metodologia or methodology chapter.

    Click here to complete this article - How To Write Chapter Three Of Your Research Project (Research Methodology)

TESTIMONIES FROM OUR CLIENTS


Please feel free to carefully review some written and captured responses from our satisfied clients.

  • "I love what you guys are doing, your material guided me well through my research. Thank you for helping me achieve academic success."

    Sampson, University of Nigeria, Nsukka.
  • "researchwap.com is God-sent! I got good grades in my seminar and project with the help of your service, thank you soooooo much."

    Cynthia, Akwa Ibom State University .
  • "Sorry, it was in my spam folder all along, I should have looked it up properly first. Please keep up the good work, your team is quite commited. Am grateful...I will certainly refer my friends too."

    Elizabeth, Obafemi Awolowo University
  • "Am happy the defense went well, thanks to your articles. I may not be able to express how grateful I am for all your assistance, but on my honour, I owe you guys a good number of referrals. Thank you once again."

    Ali Olanrewaju, Lagos State University.
  • "My Dear Researchwap, initially I never believed one can actually do honest business transactions with Nigerians online until i stumbled into your website. You have broken a new legacy of record as far as am concerned. Keep up the good work!"

    Willie Ekereobong, University of Port Harcourt.
  • "WOW, SO IT'S TRUE??!! I can't believe I got this quality work for just 3k...I thought it was scam ooo. I wouldn't mind if it goes for over 5k, its worth it. Thank you!"

    Theressa, Igbinedion University.
  • "I did not see my project topic on your website so I decided to call your customer care number, the attention I got was epic! I got help from the beginning to the end of my project in just 3 days, they even taught me how to defend my project and I got a 'B' at the end. Thank you so much researchwap.com, infact, I owe my graduating well today to you guys...."

    Joseph, Abia state Polytechnic.
  • "My friend told me about ResearchWap website, I doubted her until I saw her receive her full project in less than 15 miniutes, I tried mine too and got it same, right now, am telling everyone in my school about researchwap.com, no one has to suffer any more writing their project. Thank you for making life easy for me and my fellow students... Keep up the good work"

    Christiana, Landmark University .
  • "I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!."

    Musa, Federal University of Technology Minna
  • "I was scared at first when I saw your website but I decided to risk my last 3k and surprisingly I got my complete project in my email box instantly. This is so nice!!!."

    Ali Obafemi, Ibrahim Badamasi Babangida University, Niger State.
  • To contribute to our success story, send us a feedback or please kindly call 2348037664978.
    Then your comment and contact will be published here also with your consent.

    Thank you for choosing researchwap.com.